Yay! These things are absolutely massive since they don’t need to fit under bridges. I wonder how many mega watts these ones are. The largest ones are like 16MW each.
According to their website 12 turbines generating a total of 132MW => 11MW each
So not the largest available but then again that’s likely better for cost
Looks like about 2MW is average for on shore, so these are still massive! https://css.umich.edu/publications/factsheets/energy/wind-energy-factsheet
Still pretty amazing. Means each turbine alone will power around 10k homes.
whats the repercussions of this footprint wise? According to google a 2Mw turbine requires 0.006 km², so a 0.33Gwc of capacity per km². i wonder also how long does a windmill work per day, when averaged yearly …
deleted by creator
This is the best summary I could come up with:
Sword-shaped blades as long as a football field lie stacked along one edge, while towering yellow and green cranes hoist giant steel cylinders to stand like rockets on a launchpad.
But the weather offshore — sometimes, it can be too windy to build a wind farm — as well as all sorts of mechanical matters and a simmering labor dispute at the pier could delay the flow of power from the ocean to Long Island.
Once one of the structures is intact, crew members from a supply ship will enter the tower and, ascending on a three-passenger elevator tucked inside, tighten bolts and connect cables to prepare the turbine to generate power.
Last Monday, New York’s governor, Kathy Hochul, announced that the installation of the first South Fork turbine marked “a momentous step” toward the state’s goal of getting 70 percent of its electricity from renewable sources by 2030.
Mr. Hammond has overseen the remaking of the state-owned pier, which sits at the mouth of the Thames River across from General Dynamics’ Electric Boat submarine shipyard, into a hub for the assembly of offshore wind turbines.
“Connecticut’s deepwater ports, direct water access and long history of advanced manufacturing make our state a natural home for offshore wind projects serving all of New York and New England,” Mr. Lamont said in October.
The original article contains 1,324 words, the summary contains 221 words. Saved 83%. I’m a bot and I’m open source!